After the flurry of excitement getting the shell of the building up, we had a week of preparation for the next stages of the build.
The first task was to get the roof sorted out - it needs to be
waterproofed before the sedum finish can be installed. To prepare for this, the
roof has to have a ply deck added which will then be waterproofed with liquid
rubber.
This week, work on the blue brick external plinth wall started and
the hunt for the timber cladding began. The material finishes have to be agreed
with Planning before the facades can be completed.