Work continues inside with the dry lining of the walls, and the start of the electrical and plumbing first fix. The windows went in, looking and feeling great. The mechanism on the big window seat sliding window is both smooth and assured. We are pleased with the colour of the front door as it should complement the red colour of the sedum very well in winter. Unfortunately the big bi-folding door can not be put in as the scaffolding is in the way - that will have to wait till next week. The ply deck of the roof is finished, with all the upstands for the solar panel frames - giving an indication of the extent of PV that we will have.
Tuesday, 9 October 2012
Build Week 9 - Windows
This week saw the arrival of the much anticipated windows. These are the Internorm Edition version. We particularly chose these as they are timber / aluminium composite and have a very high thermal performance. They are triple glazed, with a thermal performance of around twice the requirement - for those in the know they achieve a u-value of 0.74. They are essentially timber windows but have an insulated aluminium facing externally, which means that they will require minimal maintenance and last very well.
Work continues inside with the dry lining of the walls, and the start of the electrical and plumbing first fix. The windows went in, looking and feeling great. The mechanism on the big window seat sliding window is both smooth and assured. We are pleased with the colour of the front door as it should complement the red colour of the sedum very well in winter. Unfortunately the big bi-folding door can not be put in as the scaffolding is in the way - that will have to wait till next week. The ply deck of the roof is finished, with all the upstands for the solar panel frames - giving an indication of the extent of PV that we will have.
Work continues inside with the dry lining of the walls, and the start of the electrical and plumbing first fix. The windows went in, looking and feeling great. The mechanism on the big window seat sliding window is both smooth and assured. We are pleased with the colour of the front door as it should complement the red colour of the sedum very well in winter. Unfortunately the big bi-folding door can not be put in as the scaffolding is in the way - that will have to wait till next week. The ply deck of the roof is finished, with all the upstands for the solar panel frames - giving an indication of the extent of PV that we will have.
Sunday, 30 September 2012
Build Week 8 - Transition
The first task was to get the roof sorted out - it needs to be
waterproofed before the sedum finish can be installed. To prepare for this, the
roof has to have a ply deck added which will then be waterproofed with liquid
rubber.
This week, work on the blue brick external plinth wall started and
the hunt for the timber cladding began. The material finishes have to be agreed
with Planning before the facades can be completed.
Sunday, 23 September 2012
Build Week 7 - SIPS Structure Complete
This has been a very exciting week as the SIPS structure is now up. Being able to walk into the completed shell is really pleasing. All of the spaces and natural light within them have turned out exactly as imagined.
The final walls went up very quickly. The roof panels were fixed into manageable pieces on the ground prior to the arrival of the crane. On Friday the 36 tonne city crane turned up and the glulam beams and roof pieces were hoisted into place.The glulam beams look terrific and when they are oiled up will be a fabulous feature of the house.
It is always surprising how the size and scale of the building changes throughout the construction process. Before the roof went on, the building felt very tall - something we tried very hard to avoid. However the roof going on made it all proportionate. The roof has also transformed the large south opening and seems to make it much bigger. We are now able to stand in the opening, soak up the view and imagine how amazing it will be to use the balcony and enjoy the views all year round.
It is always surprising how the size and scale of the building changes throughout the construction process. Before the roof went on, the building felt very tall - something we tried very hard to avoid. However the roof going on made it all proportionate. The roof has also transformed the large south opening and seems to make it much bigger. We are now able to stand in the opening, soak up the view and imagine how amazing it will be to use the balcony and enjoy the views all year round.
Sunday, 16 September 2012
Build Week 6 - SIPS start
The next 2 weeks are the biggest of the project so far. When the SIPS shell has gone up all the other elements of the build can start, a real turning point and also we will feel like we have a house.
First of all the sole plate is laid onto the low level masonry. Discrepancies in level are sorted by using plastic shims to bring the sole plate up to the highest level.Once this is in place the insulated panels fit together just like a puzzle. Each is numbered and are assembled to the instruction drawings of the supplier, Glosfords. The panels are literally stuck together with glue which creates an airtight seal. It all happens extremely quickly with brief pauses to fit lintel beams over windows. The internal walls arrive already assembled and are just fitted into place.

The posi-joists for the floor are fitted and the then the floor deck goes on. Posi-joists are two smaller pieces of timber that are connected with a metal web. These give better strength than solid timber and allow services to be channelled through the floor construction.


We finish the week with the lower ground floor completed, the ground floor and some of its walls in place.
First of all the sole plate is laid onto the low level masonry. Discrepancies in level are sorted by using plastic shims to bring the sole plate up to the highest level.Once this is in place the insulated panels fit together just like a puzzle. Each is numbered and are assembled to the instruction drawings of the supplier, Glosfords. The panels are literally stuck together with glue which creates an airtight seal. It all happens extremely quickly with brief pauses to fit lintel beams over windows. The internal walls arrive already assembled and are just fitted into place.
We finish the week with the lower ground floor completed, the ground floor and some of its walls in place.
Sunday, 9 September 2012
Build Week 5 - Beam & Block Floor
This week the floor structure went in. We chose to have a beam & block floor structure so we could use the existing foundations and allow ventilation and drainage to the basement walls. We used a specialist polystyrene block instead of the conventional concrete building block. Although more expensive it has many benefits over the traditional system. Expanded polystyrene it is a very good insulant, requiring little extra insulation to bring it up to the very high standard we set ourselves. This along with its T profile, which lets it sit in between and on top of the beam, means that the floor construction depth is reduced. The product uses a wider beam spacing meaning less beams, saving time and money. The polystyrene blocks are manufactured in 2.5m lengths and are easy to cut and fit into place, again saving time, money and a lot of work. This floor construction also scores A+ on the BRE green guide contributing to the CfSH materials assessment.
The day that the beams arrived was a very tough one as there was torrential rain all morning. Luckily we had hired a crane for the morning to lift the beams from the lorry directly onto the low level masonry. In hindsight we would have struggled greatly without the crane as the torrential rain made the clay ground very slippery and dangerous. As it was we managed to get the beams in place by lunchtime and could retire for the day absolutely soaked to the skin, but with all the beams insitu. The next day the polystyrene blocks were delivered and were quickly fitted into place. A job well done in difficult circumstances. The rest of the week was spent finishing the low level masonry in preparation for the SIPS installation..........
Sunday, 2 September 2012
Build Week 4 - More Groundworks
A week spent continuing with the preparation for the SIPS erection. The site is taking shape and we are now getting a definite feel for the footprint. Now that the plan is becoming much more defined there is a much greater feel for the size of the house. When everything is open it feels like it is very small, but as it rises out of the ground it gives a much better indication for actually how big it is. There was more excavation and the concrete was poured for the external shed and rainwater tank foundation pad.

| Tanking base drain rodding point |
With the low level masonry going up, and following a meeting with the SIPS installers on site, the project programme is starting to firm up. Some time has been spent planning in all the next phases of the project. This has been very positive as we can now see that if things go according to plan we should get a finished envelope in a couple of months time and an idea of when the main internal works will be done.
Tuesday, 28 August 2012
CfSH - Level 6 Design Stage Certificate
We have received the Code for Sustainable Home design stage assessment certificate - officially achieving the top rating of level 6.
It is practically impossible to score maximum points everywhere, however we scored maximum credits in 5 of the 9 sections. We dropped a point in the energy section, most of which should be recovered in the post-construction assessment following the air pressure test. Another point was dropped in materials due to using timber/aluminium composite windows. Points were also dropped in the management section as we chose not to take part in the considerate constructors scheme and key point indicators due to the extra financial costs they would incur. Some points were also dropped in the ecology section, some of which are only applicable for taller developments. There is an extra credit we could achieve through extensive ecological enhancement, should we need to.
We are really pleased and proud of what we have achieved here.
It is practically impossible to score maximum points everywhere, however we scored maximum credits in 5 of the 9 sections. We dropped a point in the energy section, most of which should be recovered in the post-construction assessment following the air pressure test. Another point was dropped in materials due to using timber/aluminium composite windows. Points were also dropped in the management section as we chose not to take part in the considerate constructors scheme and key point indicators due to the extra financial costs they would incur. Some points were also dropped in the ecology section, some of which are only applicable for taller developments. There is an extra credit we could achieve through extensive ecological enhancement, should we need to.
We are really pleased and proud of what we have achieved here.